📈 Live Market Tracking
Every NSE and BSE corporate filing, read and explained by AI within minutes — impact, key figures, short/long-term view and what to watch.
Live · AI analyzer runs every 5 min (07:00–23:55 IST)
0 analysed today
FollowTelegram
0
Today
152,139
All-time analysed
43,645
Positive
6,747
Negative
92,898
Neutral
8,781
Watch
📊 Last 7 days — analysed filings by sentiment
Note: These are AI-generated, educational summaries of public NSE
filings — grounded in each document, but not investment advice and possibly incomplete.
Verify against the original filing and consult a SEBI-registered adviser before acting.
118 announcements match the current filters (relevance ≥ 5).
ACME Solar Commissions Phase IV of 32.366 MW BESS Project in Rajasthan
ACME Solar Holdings Limited, through its subsidiary ACME Surya Power Private Limited, has commissioned the fourth phase of its Battery Energy Storage System (BESS) project in Bikaner, Rajasthan. This phase adds 32.366 MW / 145.435 MWh to the company's operational portfolio, with commercial operations scheduled to begin on April 15, 2026. This milestone brings the total commissioned capacity for this specific project to 139.509 MW / 626.875 MWh. The expansion enhances the company's revenue-generating assets in the high-growth energy storage sector.
Key Highlights
Commissioned 32.366 MW / 145.435 MWh capacity in Phase IV of the BESS project
Commercial Operation Date (COD) for the new phase is set for April 15, 2026
Total commissioned capacity for the project reached 139.509 MW / 626.875 MWh
Project is located at Village Jaimalsar, District Bikaner, Rajasthan
👀 What to Watch
Investors should look favorably on this capacity addition as it directly contributes to the company's operational revenue. Monitor the execution of remaining project phases to gauge long-term growth trajectory.
ACME Solar Commissions 32.366 MW Phase-IV BESS Project in Rajasthan
ACME Solar Holdings Limited has successfully commissioned the fourth phase of its Battery Energy Storage System (BESS) project in Bikaner, Rajasthan. This phase adds 32.366 MW / 145.435 MWh of capacity through its subsidiary, ACME Surya Power Private Limited. The commercial operation date for this phase is set for April 15, 2026. This milestone brings the total commissioned capacity of the project to 139.509 MW / 626.875 MWh, demonstrating steady progress in the company's operational expansion.
Key Highlights
Commissioned 32.366 MW / 145.435 MWh capacity in the fourth phase of the BESS project
Commercial Operation Date (COD) for Phase-IV is scheduled for April 15, 2026
Total commissioned capacity for the subsidiary now reaches 139.509 MW / 626.875 MWh
Project is strategically located at Village Jaimalsar, Bikaner district, Rajasthan
👀 What to Watch
Investors should monitor the revenue contribution from these newly commissioned phases in upcoming quarterly results. The successful execution of large-scale battery storage projects strengthens the company's position in the renewable energy transition.
ACME Solar Commissions Additional 4 MW Wind Capacity; Total Project Reaches 96 MW
ACME Solar Holdings Limited, through its subsidiary ACME Eco Clean Energy Private Limited, has commissioned an additional 4 MW of wind power capacity in Gujarat. This is part of a larger 100 MW wind power project located in the Surendranagar district. With this latest addition, the total commissioned capacity for this specific project has reached 96 MW. The commissioning has been verified by state agencies GEDA and PGVCL, marking the near-completion of the project and moving it closer to full revenue generation.
Key Highlights
Commissioned 4 MW additional wind power capacity at Titoda, Gujarat.
Total commissioned capacity for the project now stands at 96 MW out of 100 MW.
Project is being executed by subsidiary ACME Eco Clean Energy Private Limited.
Commissioning witnessed and confirmed by GEDA and PGVCL officials.
👀 What to Watch
Investors should view this as a positive operational milestone that brings the 100 MW project to 96% completion. Monitor for the final 4 MW commissioning to mark the full operational status of this asset.
ACME Solar Commissions 33.33 MW Phase-IV of Rajasthan Battery Storage Project
ACME Solar Holdings has announced the commissioning of the fourth phase of its Battery Energy Storage System (BESS) project in Rajasthan through its subsidiary, ACME Sun Power. This phase adds 33.333 MW / 160.48 MWh of capacity, with the commercial operation date set for April 03, 2026. The company has now successfully commissioned a total of 133.336 MW out of the planned 300 MW for this specific project. This steady execution highlights the company's progress in the high-growth energy storage segment.
Key Highlights
Commissioned 33.333 MW / 160.48 MWh capacity in the fourth phase of the Rajasthan BESS project
Total commissioned capacity for this project reaches 133.336 MW / 641.980 MWh
Overall project target stands at 300 MW / 1409.34 MWh capacity
Commercial Operation Date (COD) for the fourth phase is confirmed as April 03, 2026
Project is located at Village Badi Sid, Rajasthan, and executed by a wholly owned subsidiary
👀 What to Watch
Investors should monitor the timely execution of the remaining 166.66 MW capacity as it will significantly contribute to the company's operational revenue. The successful scaling of BESS technology positions the company well in the evolving Indian renewable energy landscape.
ACME Solar Credit Rating Reaffirmed at [ICRA]AA- (Stable); Rated Amount Increased to ₹2,500 Cr
ICRA Limited has reaffirmed the long-term credit rating of ACME Solar Holdings Limited at [ICRA]AA- with a Stable outlook. The total rated amount for non-fund based facilities has been significantly enhanced from ₹1,500 crore to ₹2,500 crore. This includes an increase in existing non-fund based limits to ₹1,850 crore and a new assignment of ₹650 crore for unallocated facilities. The reaffirmation and limit enhancement indicate strong creditworthiness and support for the company's expanding operational scale.
Key Highlights
ICRA reaffirmed the long-term rating at [ICRA]AA- with a Stable outlook.
Total rated amount for non-fund based facilities increased by ₹1,000 crore to reach ₹2,500 crore.
Long-term non-fund based (Others) limit enhanced from ₹1,500 crore to ₹1,850 crore.
New rating of [ICRA]AA- (Stable) assigned to ₹650 crore of unallocated non-fund based facilities.
👀 What to Watch
Investors should take confidence in the reaffirmed high credit rating, which reflects financial stability and facilitates lower borrowing costs. The enhancement in limits suggests the company is positioning itself for larger project executions in the solar sector.
ACME Solar Commissions Phase III of 300 MW Rajasthan Battery Energy Storage Project
ACME Solar Holdings Limited, through its subsidiary ACME Sun Power Private Limited, has successfully commissioned the third phase of its Battery Energy Storage System (BESS) project in Rajasthan. This phase adds 33.333 MW / 160.51 MWh of capacity, bringing the total commissioned capacity to 100.003 MW out of the planned 300 MW. The commercial operation date for this phase is set for April 02, 2026. This milestone demonstrates steady execution of the company's large-scale energy storage strategy, which is critical for grid stability and renewable energy integration.
Key Highlights
Commissioned 33.333 MW / 160.51 MWh capacity in Phase III of the Rajasthan BESS project
Total commissioned capacity now stands at 100.003 MW / 481.500 MWh
The overall project target is 300 MW / 1409.34 MWh capacity
Commercial Operation Date (COD) for the third phase is April 02, 2026
Project is located at Village Badi Sid, Phalodi and Jodhpur districts, Rajasthan
👀 What to Watch
Investors should take this as a positive sign of operational execution and project delivery. Monitor the progress of the remaining 200 MW capacity as it will be a key driver for revenue growth in the storage segment.
Acme Solar Commissions Phase III of 250 MW BESS Project in Rajasthan
Acme Solar Holdings has successfully commissioned the third phase of its Battery Energy Storage System (BESS) project in Bikaner, Rajasthan, through its wholly-owned subsidiary. This phase adds 11.429 MW / 51.354 MWh to the operational capacity, with the Commercial Operation Date (COD) set for March 31, 2026. The total commissioned capacity for this specific project has now reached 107.143 MW out of the planned 250 MW. This milestone reflects steady execution in the company's renewable energy storage portfolio.
Key Highlights
Commissioned 11.429 MW / 51.354 MWh in the third phase of the Rajasthan BESS project
Cumulative commissioned capacity for the project now stands at 107.143 MW / 481.440 MWh
The total planned capacity for the Bikaner project is 250 MW / 1103.392 MWh
Commercial operations for this phase are scheduled to begin on March 31, 2026
Project is executed via ACME Surya Power Private Limited, a 100% owned subsidiary
👀 What to Watch
Investors should take this as a positive sign of the company's ability to execute complex energy storage projects. Monitor the progress of the remaining 143 MW capacity as it will contribute significantly to future revenue streams.
Acme Solar Receives Rs 149.73 Crore GST Demand Notice from DGGI
Acme Solar Holdings has received a Show-Cause cum Demand Notice from the DGGI, Jaipur, alleging a GST shortfall of Rs 149.73 Crores. The notice covers the period from April 2021 to March 2025 and relates to the supply of goods and services for solar power systems. The company plans to contest the demand, noting that similar notices have been issued to several other renewable energy companies. While the amount is significant, the company does not expect any immediate financial or operational impact.
Key Highlights
Total GST demand of Rs 149.73 Crores for the period April 2021 to March 2025.
Notice issued by the Directorate General of Goods & Services Tax Intelligence (DGGI), Jaipur.
Allegation involves short payment of GST on solar power generating system supplies.
Company is reviewing the notice with legal advisors and intends to contest the claim.
Management states that similar demands are being contested by other renewable energy firms.
👀 What to Watch
Investors should monitor the legal developments regarding this GST demand as it represents a significant contingent liability. No immediate action is required as the company is contesting the notice alongside industry peers.
ACME Solar Subsidiary Commissions Additional 4 MW Wind Capacity; Total Reaches 92 MW of 100 MW
ACME Solar Holdings Limited has announced that its subsidiary, ACME Eco Clean Energy Private Limited, has commissioned an additional 4 MW of wind power capacity in Gujarat. This update brings the total commissioned capacity of the specific 100 MW project to 92 MW. The commissioning took place in the Surendranagar district and has been verified by GEDA and PGVCL officials. This incremental progress demonstrates the company's steady execution towards completing its renewable energy project pipeline.
Key Highlights
Commissioned additional 4 MW wind power capacity at the Surendranagar project in Gujarat.
Total commissioned capacity for this specific project now stands at 92 MW out of the planned 100 MW.
The commissioning was witnessed and confirmed by Gujarat Energy Development Agency (GEDA) and PGVCL.
This follows a series of incremental commissionings initiated in October 2025, showing consistent project advancement.
👀 What to Watch
Investors should take note of the company's ability to consistently execute and commission capacity in phases. Monitor for the final 8 MW commissioning to mark the full completion of this 100 MW project.
ACME Solar Commissions Phase II of 35.714 MW BESS Project in Rajasthan
ACME Solar Holdings has successfully commissioned the second phase of its Battery Energy Storage System (BESS) project in Bikaner, Rajasthan, through its wholly-owned subsidiary. This phase adds 35.714 MW / 160.48 MWh to the company's operational capacity, with commercial operations starting March 26, 2026. The total commissioned capacity for this specific project now reaches 95.714 MW out of a planned 250 MW. This progress demonstrates the company's ability to execute large-scale energy storage projects, which are critical for grid stability and renewable integration.
Key Highlights
Commissioned 35.714 MW / 160.48 MWh capacity in Phase II of the Jaimalsar project
Total commissioned capacity for the project reaches 95.714 MW / 430.086 MWh
Project is part of a larger 250 MW / 1103.392 MWh BESS development pipeline
Commercial operation date (COD) for Phase II is set for March 26, 2026
Executed through 100% subsidiary ACME Surya Power Private Limited
👀 What to Watch
Investors should monitor the timely completion of the remaining 154 MW capacity of this project as a key growth driver. The successful scaling of BESS technology positions the company well in the high-growth energy storage sector.
ACME Solar Commissions 155 MW / 470 MWh BESS Projects in Rajasthan
ACME Solar Holdings has commissioned an additional 155 MW / 470.25 MWh of Battery Energy Storage System (BESS) capacity in Rajasthan. This milestone brings the company's total commissioned BESS capacity to 297.67 MW / 951.74 MWh, representing progress toward a planned 835 MW target. These projects will operate on a merchant basis, allowing the company to generate revenue through price arbitrage between peak and non-peak demand hours. The expansion strengthens ACME's integrated renewable portfolio, which currently stands at 8,071 MW including under-construction projects.
Key Highlights
Commissioned 155 MW / 470.25 MWh of additional BESS capacity in Rajasthan
Total commissioned BESS capacity reached 297.67 MW / 951.74 MWh
Projects will operate on a merchant basis to capture peak/non-peak price differentials
Total planned BESS capacity for these SPVs is 835 MW / 3,114.64 MWh
Overall portfolio includes 2,978 MW operational and 5,093 MW under construction
👀 What to Watch
Investors should monitor the revenue contribution from these merchant BESS projects to evaluate the profitability of the storage business model. The successful commissioning reflects strong execution capabilities in the high-growth energy storage sector.
ACME Solar Commissions 95 MW Phase-IV of Rajasthan Battery Energy Storage Project
ACME Solar Holdings, through its wholly owned subsidiary ACME Suryodaya Private Limited, has commissioned the fourth phase of its Battery Energy Storage System (BESS) project in Jaisalmer, Rajasthan. This phase adds 95 MW / 200.64 MWh of capacity, bringing the total commissioned capacity of the project to 171 MW / 361.14 MWh. The commercial operation date for this phase is set for March 25, 2026. This progress represents a significant step toward completing the total planned project capacity of 285 MW / 601.904 MWh.
Key Highlights
Commissioned 95 MW / 200.64 MWh capacity in Phase IV of the BESS project in Rajasthan.
Total commissioned capacity for the project has reached 171 MW / 361.14 MWh.
The project is being executed by a 100% owned subsidiary, ACME Suryodaya Private Limited.
Commercial operations for this phase are scheduled to commence on March 25, 2026.
The total target capacity for the entire BESS project is 285 MW / 601.904 MWh.
👀 What to Watch
Investors should note this as a positive operational milestone that will likely enhance revenue from the next quarter. Monitor the timely commissioning of the remaining 114 MW capacity to ensure the project reaches full scale as planned.
ACME Solar Commissions 95 MW Phase IV of BESS Project in Rajasthan
ACME Solar Holdings has announced the commissioning of the fourth phase of its Battery Energy Storage System (BESS) project in Jaisalmer, Rajasthan, through its subsidiary ACME Suryodaya Private Limited. This phase adds 95 MW / 200.64 MWh of capacity, with the Commercial Operation Date (COD) set for March 25, 2026. The total commissioned capacity for this specific project has now reached 171 MW / 361.14 MWh out of a total planned 285 MW / 601.904 MWh. This operational milestone signifies steady progress in the company's renewable energy storage portfolio, which is critical for grid stability and revenue growth.
Key Highlights
Commissioned 95 MW / 200.64 MWh capacity in the fourth phase of the Rajasthan BESS project
Total commissioned capacity for the project stands at 171 MW / 361.14 MWh
Commercial Operation Date (COD) for Phase IV is scheduled for March 25, 2026
Project is executed by ACME Suryodaya Private Limited, a wholly owned subsidiary
Remaining 114 MW / 240.764 MWh capacity is yet to be commissioned to reach the 285 MW target
👀 What to Watch
Investors should monitor the timely completion of the remaining 114 MW capacity as it will further boost the company's operational revenue. The successful execution of BESS projects positions ACME Solar well in the evolving Indian renewable energy market.
ACME Solar Commissions Additional 4 MW Wind Capacity; Total Project Reaches 88 MW
ACME Solar Holdings Limited's subsidiary, ACME Eco Clean Energy Private Limited, has successfully commissioned an additional 4 MW of its 100 MW wind power project in Gujarat. This update brings the total commissioned capacity of this specific project to 88 MW out of the planned 100 MW. The commissioning has been verified by Gujarat Energy Development Agency (GEDA) and Paschim Gujarat Vij Company Limited (PGVCL). This progress reflects the company's steady execution of its renewable energy pipeline.
Key Highlights
Commissioned 4 MW additional wind power capacity in Surendranagar, Gujarat
Total commissioned capacity for this specific project now stands at 88 MW out of 100 MW
Project verified and confirmed by state agencies GEDA and PGVCL
Follows a series of incremental commissioning updates since October 2025
👀 What to Watch
Investors should take note of the steady project execution which will lead to incremental revenue growth. Monitor the timeline for the remaining 12 MW capacity to complete the project.
ACME Solar Commissions Additional 8 MW Wind Capacity; Total Reaches 84 MW of 100 MW Project
ACME Solar Holdings Limited announced that its subsidiary, ACME Eco Clean Energy Private Limited, has commissioned an additional 8 MW of wind power capacity in Gujarat. This update brings the total commissioned capacity of the 100 MW wind project to 84 MW. The commissioning was witnessed by state energy officials from GEDA and PGVCL, with formal certification expected shortly. This progress marks a steady advancement toward the full operationalization of the project, contributing to the company's renewable energy portfolio.
Key Highlights
Commissioned 8 MW additional wind power capacity in Surendaranagar, Gujarat.
Total commissioned capacity for the project now stands at 84 MW out of 100 MW.
Project executed by subsidiary ACME Eco Clean Energy Private Limited.
Commissioning witnessed and confirmed by GEDA and PGVCL officials.
👀 What to Watch
Investors should view this as a positive step in project execution and monitor the timeline for the remaining 16 MW. The incremental capacity addition will contribute to the company's revenue generation from renewable energy.
ACME Solar Commissions 143 MW / 481 MWh Battery Energy Storage System in Rajasthan
ACME Solar Holdings has commissioned 142.67 MW / 481.49 MWh of Battery Energy Storage System (BESS) in Rajasthan, representing Phase-1 of a 585 MW planned project. The system is currently connected to the Inter-State Transmission System and will operate on a merchant basis to capture revenue from peak-hour price differentials. This commissioning is a significant step toward the company's massive ~17 GWh BESS requirement across its portfolio. Eventually, these units will be integrated into Firm and Dispatchable Renewable Energy (FDRE) projects under 25-year PPAs.
Key Highlights
Commissioned 142.67 MW / 481.49 MWh BESS in Rajasthan as part of Phase-1.
Total planned capacity for the current SPVs stands at 585 MW / 2011.24 MWh.
Company has a total under-construction contracted capacity of 5,105 MW including ~16.5 GWh of BESS.
Initial revenue will be generated through merchant trading based on peak and non-peak demand spreads.
The project will eventually transition to a 25-year PPA model via integration with FDRE projects.
👀 What to Watch
Investors should view this as a positive milestone in ACME Solar's transition toward becoming a provider of dispatchable power. Monitor the execution of the remaining 16.5 GWh BESS pipeline as it will be a key driver for long-term revenue stability.
ACME Solar Commissions 33.335 MW Phase II of Rajasthan BESS Project
ACME Solar Holdings, through its wholly owned subsidiary ACME Sun Power Private Limited, has commissioned the second phase of its 300 MW Battery Energy Storage System (BESS) project in Rajasthan. This phase contributes 33.335 MW / 160.51 MWh to the total project, with the commercial operation date set for March 14, 2026. To date, the company has successfully commissioned a total of 66.67 MW / 320.99 MWh of the planned 300 MW capacity. This milestone reflects steady execution in the high-potential energy storage segment.
Key Highlights
Commissioned 33.335 MW / 160.51 MWh as part of Phase II of the Rajasthan BESS project
Total commissioned capacity for this specific project now stands at 66.67 MW / 320.99 MWh
Commercial Operation Date (COD) for the second phase is confirmed for March 14, 2026
The project is located at Village Badi Sid, Rajasthan, and is managed by a wholly owned subsidiary
👀 What to Watch
Investors should view this as a positive step in the company's operational ramp-up and monitor the timeline for the remaining 233.33 MW capacity. Successful execution of BESS projects is critical for the company's long-term valuation in the renewable energy sector.
ACME Solar Signs PPAs for 450 MW / 1800 MWh Peak Power Project with SJVN
ACME Solar, through its subsidiary, has signed two 25-year Power Purchase Agreements (PPAs) with SJVN for a total capacity of 450 MW / 1,800 MWh. The project ensures 4 hours of peak power supply during non-solar hours with a 90% availability requirement on a monthly and annual basis. This agreement brings the company's total PPA signed capacity to 6,270 MW, with 1,690 MW signed in the current financial year alone. The project will utilize existing night-time connectivity in Rajasthan's high irradiation zones to optimize operational efficiency.
Key Highlights
Signed two 25-year PPAs with SJVN for 450 MW / 1,800 MWh of assured peak power
Total PPA signed capacity increased to 6,270 MW, with 1,690 MW added in the current FY
Guarantees 4 hours of peak power supply during non-solar hours with 90% availability
Under-construction PPA signed portfolio now stands at 3,304 MW
Project to leverage high irradiation zones in Rajasthan and existing ISTS connectivity
👀 What to Watch
This development provides long-term revenue visibility and strengthens ACME Solar's position in the high-growth energy storage and peak power segment. Investors should monitor the execution progress of the 3,304 MW under-construction portfolio for timely commissioning.
ACME Solar Commissions Phase III of 19 MW / 40.50 MWh BESS Project in Rajasthan
ACME Solar Holdings Limited has announced the commissioning of the third phase of its Battery Energy Storage System (BESS) project in Jaisalmer, Rajasthan, through its subsidiary ACME Suryodaya Private Limited. This phase adds 19 MW / 40.50 MWh of capacity, with the Commercial Operation Date (COD) scheduled for March 13, 2026. With this addition, the total commissioned capacity of the project has reached 76 MW / 160.50 MWh. The company is working towards a total project target of 285 MW / 601.904 MWh, indicating steady progress in its renewable energy infrastructure.
Key Highlights
Commissioned 19 MW / 40.50 MWh capacity in Phase III of the Rajasthan BESS project
Total commissioned capacity for the project now stands at 76 MW / 160.50 MWh
Commercial Operation Date (COD) for the new phase is set for March 13, 2026
The project is being executed by wholly owned subsidiary ACME Suryodaya Private Limited
Total planned capacity for the Jaisalmer project is 285 MW / 601.904 MWh
👀 What to Watch
Investors should take note of the company's consistent execution in the high-growth energy storage segment. Continued progress toward the full 285 MW capacity will likely enhance revenue visibility and operational scale.
ACME Solar Commissions 4 MW Wind Power Capacity of 100 MW Project in Gujarat
ACME Solar Holdings Limited has announced that its subsidiary, ACME Eco Clean Energy Private Limited, has commissioned 4 MW of wind power capacity. This capacity is part of a larger 100 MW wind power project located in Surendranagar, Gujarat. The company received the official Certificate of Commissioning from the Gujarat Energy Development Agency (GEDA) on March 09, 2026. This development marks incremental progress in the company's renewable energy operational portfolio.
Key Highlights
Commissioned 4 MW wind power capacity out of a total 100 MW project
Project located at Village Garambhadi, Surendranagar district, Gujarat
Certificate of Commissioning received from Gujarat Energy Development Agency (GEDA)
Executed through subsidiary ACME Eco Clean Energy Private Limited
👀 What to Watch
Investors should monitor the execution timeline for the remaining 96 MW of the project. This incremental commissioning demonstrates steady progress in the company's wind energy segment.