📈 Live Market Tracking
Every NSE and BSE corporate filing, read and explained by AI within minutes — impact, key figures, short/long-term view and what to watch.
Live · AI analyzer runs every 5 min (07:00–23:55 IST)
Latest filing: 2026-09-28 20:35
0 analysed today
FollowTelegram
0
Today
152,076
All-time analysed
43,619
Positive
6,746
Negative
92,864
Neutral
8,779
Watch
📊 Last 7 days — analysed filings by sentiment
Note: These are AI-generated, educational summaries of public NSE
filings — grounded in each document, but not investment advice and possibly incomplete.
Verify against the original filing and consult a SEBI-registered adviser before acting.
1 announcement match the current filters (relevance ≥ 5).
NACDAC Wins ₹13.46 Cr Order Enhancement, Boosting Project Value by 64.2% to ₹34.43 Cr
NACDAC Infrastructure has secured an order enhancement of ₹13.46 crore from Uttarakhand Pey Jal Sansadhan Vikas Evam Nirman Nigam for its ongoing bus terminal and workshop building project in Ramnagar, Nainital. This extra-item sanction represents a 64.2% expansion over the original contract value of ₹20.97 crore, bringing the revised project total to approximately ₹34.43 crore (excluding GST). The incremental ₹13.46 crore contract represents ~12.0% of the company's TTM revenue of ₹112 crore, and ~21.3% of FY26 revenue. Execution of these extra items is scheduled for completion by March 2027.
Confidence: HIGH
What changedSanction of extra works amounting to ₹13.46 crore on an existing pre-IPO contract, raising the overall contract size to ₹34.43 crore.
Why it mattersProvides revenue visibility of ~12% of TTM revenue through FY27 without requiring additional bidding or client acquisition costs.
Enhancement order value: ₹13,46,46,477Original contract value: ₹20.97 croreRevised contract value: approx. ₹34.43 croreContract value increase: approx. 64.2%Enhancement vs TTM revenue: ~12.0%Execution deadline: March 2027
📅 Short termPositive sentiment driver as the order book expands with zero customer acquisition costs on an existing active site.
📈 Long termSupports medium-term top-line visibility through FY27, demonstrating capability to scale scope in state infrastructure projects.
⚠ Risk flags
- Execution risk within the March 2027 timeline
- Government counterparty payment delays subject to actual quantities executed
Key Highlights
Received order enhancement sanction worth ₹13,46,46,477 (excluding GST)
Contract value increased by 64.2% from ₹20.97 crore to approx. ₹34.43 crore
Scope covers civil, MEP, HVAC, firefighting, and pumping works at U.T.C., Ramnagar
Execution timeline for the enhanced order is set up to March 2027
👀 What to Watch
Track execution progress and billing milestones for the Ramnagar bus terminal project leading up to March 2027, as well as working capital deployment.